phase, verified, status, score, overrides_applied, re_verification, gaps, deferred, human_verification
phase verified status score overrides_applied re_verification gaps deferred human_verification
08-alt-landmark-preprocessing-routing-backend-v2 2026-10-25T14:43:22Z gaps_found 1/3 roadmap success criteria (SC-2 ✓; SC-1 ✗; SC-3 ✗ as written — correctly not taken). All 5 plans' machinery must-haves verified. 0
previous_status previous_score gaps_closed gaps_remaining regressions
none n/a
SC-1: longest KL-metro routes route within the free-plan CPU budget
SC-3: the c3 degradation class retires
truth status reason artifacts missing
Longest KL-metro routes route within the free-plan CPU budget (p95 under the 8 ms ceiling, measured by the existing CPU gate) — SC-1 failed The measured verdict is a FAIL and stayed a FAIL through the pre-committed ladder: p95 152.788 ms (25-route CI gate) / 185.692 ms (D-04 extended 100-pair verdict) vs the 8 ms budget on the campaign host; this verifier's own re-run measured p95 107.493 ms — same band, same honest FAIL. The L=32 ladder rung measured worse (182.725 / 204.499 ms). Post-F1, ALT is INERT on the current binary by design: 0/24 landmark toTable columns are sentinel-clean (the 6,285-node island, 2.02% of cells), so potentials degrade to exactly haversine and the pre-ALT CPU band returned. The theoretically sound fast configuration (direction-split potentials π_f/π_r with a re-proven bidirectional meet rule) is search-skeleton work that Phase 8's own untouchable lines (stop rule, reductions, alternation, meet probes, reconstruction) forbid. Every number is quoted verbatim into docs/BUDGETS.md, docs/KNOWN-LIMITATIONS.md, docs/ROAD-GRAPH.md, and scripts/lib/budget-gates.mjs (drift guard 400 ms; the 8 ms budget unchanged, its FAIL still printed).
path issue
routing/scripts/measure-route-cpu.mjs None — the gate is honest and healthy (P95_BUDGET_MS = 8 unchanged; prints GATE FAIL). The gap is the measured number, not the tool.
path issue
routing/src/astar.ts ALT potentials are sound-but-inert on this binary (clean-columns-only F1 law; 0/24 clean columns). Making them fast requires direction-split potentials — code outside this phase's sanctioned surface.
USER STRATEGIC DECISION (not a fix plan): pick the escalation track recorded in docs/BUDGETS.md §c3 and 08-05-SUMMARY — (1) direction-split potentials with a re-proven bidirectional meet rule (search-skeleton work; needs its own planned phase with the BH meet rule re-proven), (2) Contraction Hierarchies (the Phase-6 deferral, the Malaysia-scale tier), (3) Workers Paid (rejected by the $0 law — reversal needs explicit sign-off), or (4) keep c3 as the designed degradation (the current shipped posture: router-pending on long cross-metro reroutes). Option 4 is the only one requiring zero further code.
truth status reason artifacts missing
The budget record's c3 degradation class retires; KNOWN-LIMITATIONS updated — SC-3 failed The retirement half of the criterion did NOT happen — correctly: the pre-committed law (retirement never fires on failing numbers) forbids it, and SC-1 failed. The record-update half IS complete and honest: KNOWN-LIMITATIONS' cross-metro section is the /cari-shaped post-ALT record (WHAT CHANGED / what REMAINS, quoted gate lines), its ALT roadmap-pointer row reads 'Built (Phase 8, 2026-10-25): optimality verified; the CPU verdict measured over budget', BUDGETS and ROAD-GRAPH carry the same quoted numbers, and 'next-milestone' wording is purged everywhere (grep = 0 across all four records).
path issue
docs/KNOWN-LIMITATIONS.md None — the honest record is exactly what D-05's fail branch prescribes. Retirement is contingent on SC-1 and cannot honestly happen while it fails.
Contingent on the SC-1 decision above: only after a passing CPU verdict does a closure plan rewrite these records as a retirement.
test expected why_human
Decide the c3 escalation track (the gap above): direction-split potentials / CH / Workers Paid reversal / keep c3. A maintainer decision recorded against docs/BUDGETS.md §c3; if 'keep c3', Phase 9+ proceed with the current honest-degradation posture; if a code track, it becomes a planned phase of its own. Strategic trade-off between $0 law, scope, and schedule — not verifiable from the codebase.
test expected why_human
Verify the R2 migration state: the shipped decode path is ARG2-ONLY (D-01), so if the R2 object kl-roadgraph.v1.bin still holds ARG1 bytes, the deployed Worker returns router-pending for EVERY route until the rebuilt binary is uploaded once. Run `node routing/scripts/upload-road-graph.mjs` then the `--check` roundtrip against R2 (maintainer-time, account-gated). The R2 object decodes as ARG2 (version 2, L=24, coverage 0.980) and production /api/route serves real routes again. R2 contents and deploy state are outside the repo; the upload is deliberately a manual, account-validated act.

Phase 8: ALT Landmark Preprocessing (Routing Backend v2) — Verification Report

Phase Goal: Cross-metro routes route in-budget on the free plan: ALT (A*, Landmarks, Triangle-inequality) preprocessing over the CSR graph upgrades engine A's worst case while staying $0 — the c2 rung of the measured ladder, executed. Verified: 2026-10-25T14:43:22Z Status: gaps_found Re-verification: No — initial verification

Goal Achievement — the honest verdict

The phase's machinery landed completely and at high quality: ARG2 codec, landmark preprocessing, ALT steering, build-stage integration, the D-03 optimality gate, and every record rewritten honestly. The phase's core measurable deliverable did not land: the CPU verdict is a FAIL (p95 107–186 ms across hosts/modes vs the 8 ms budget), the pre-committed ladder ran to its documented stop, and the debug session proved the wall is structural (ALT inert on this binary; the fast configuration is provably unsound under the shared-average BH; the fix is out-of-constraint skeleton work). SC-2 (optimality) is the one success criterion achieved — and it was hard-won: the phase's own gates caught and fixed two real suboptimality bugs (Rule-1 fromTable, RC-1 per-node sentinel skip → F1).

This is the honest-FAIL branch the plan pre-committed to, executed faithfully. The gap that remains is a maintainer strategic decision, not a defect a closure plan can silently fix.

Observable Truths (roadmap contract)

# Truth Status Evidence
1 SC-1: Longest KL-metro routes route within the free-plan CPU budget (p95 under the ceiling, measured by the existing CPU gate) ✗ FAILED Campaign: GATE FAIL: p95 152.788 ms exceeds the 8 ms budget (A1) + extended GATE FAIL: p95 185.692 ms (n=53); L=32 probe worse (182.725 / 204.499). This verifier re-ran the gate: GATE FAIL: p95 107.493 ms exceeds the 8 ms budget — same honest band. Post-F1 ALT is inert on the current binary (0/24 clean toTable columns — the 6,285-node island), so the c2 rung bought no measured CPU improvement.
2 SC-2: Route optimality unaffected (ALT admissible — corpus re-run green with identical tolerance verdicts) ✓ VERIFIED Re-ran both gates this session: D-03 gate GATE PASS: 53/53 routed pairs equal within ±0.1%, verdict classes preserved (100/100 record pairs; 6 unreachable + 41 unsnappable preserved, 0 re-snapped), 0 violations, max |Δ| 0.005%, epsilon mirror intact; oracle sweep GATE PASS: 0/200 |Δ| violations (182 routed, 18 unreachable, worst |Δ| +0.000%) on fresh seed-0x08f1 pairs the fixed corpus structurally cannot cover. routing:test 82/82 (incl. A1 625-pair Dijkstra-equivalence, A11/A12/A13 pins).
3 SC-3: The budget record's c3 degradation class retires; KNOWN-LIMITATIONS updated ✗ FAILED (as written — correctly not taken) Retirement never fires on failing numbers (the pre-committed law). The update half IS done: KNOWN-LIMITATIONS carries the quoted post-ALT record, the ALT row reads "Built (Phase 8, 2026-10-25): optimality verified; the CPU verdict measured over budget — the degradation stands"; "next-milestone" purged from all four records (grep = 0).

Score: 1/3 roadmap success criteria. (All five plans' machinery must-haves — ARG2 codec laws, landmark module, ALT containment, build-stage integration, gates + records — verified; see below.)

Score note: SC-3's failure is compliant behavior, not neglect — the criterion is arithmetically unreachable while SC-1 fails, and faking it would have violated the phase's own honest-engineering law. It is nonetheless reported as not-achieved because the class did not retire.

Plan-Level Machinery (must_haves from the 5 PLANs — all verified)

Plan Claimed machinery Verified evidence
08-01 Pre-ALT baseline frozen BEFORE the codec; ARG1 guard; --extended D-04 flag; default mode byte-compatible measure-optimality-baseline.mjs refuses non-ARG1 binaries (version check at L153–155); alt-baseline.json is coordinate-pinned (origin/destination lat-lng, never node indices) with the epsilon block {name: OPTIMALITY_EPSILON_PCT, pct: 0.1}; --extended imports generateCrossMetroPairs from the baseline module (ONE pair-set definition, two consumers); P95_BUDGET_MS = 8 grep = 1
08-02 ARG2 codec, exact-size-before-allocation, ARG1→null, fixture regenerated through the ONE encode path, landmark.ts the single table authority graph.ts: magic 0x41524732, version 2, landmarkCount/landmarkQuantumS/landmarkTo/landmarkFrom fields, buffer.byteLength !== lay.total → null at L228 (before view allocation); graph.test.mjs:139 consumes mini-graph-arg1.bin as the rejection vector; mini-graph.bin regenerated (1668→1884 B); landmark.ts exports farthestPointAnchors/landmarkTables/landmarkCoverage + LANDMARK_QUANTUM_S/MAX_QUANTA/I32_WEIGHT_CEILING (WR-04 fix present)
08-03 ALT inside the proven BH skeleton; clean-columns containment (F1); rollout locks astar.ts: cleanColumnsFor (L233) + search-scoped activeL (L358–362), LANDMARK_SENTINEL_U16 named constant, haversine max-fallback; landmarkFrom appears ZERO times in astar.ts (the A11 law — stronger than required); rollout.test.mjs RO1/RO2 structural pins ran green in the suite; worker-router.ts and upload-road-graph.mjs contain no version/format branches (grep = 0)
08-04 Build preprocessing stage via the ONE landmark module; D-02 scaling rule; honest gates; --check build-road-graph.mjs: imports the landmark module (never re-implements Dijkstra), NODES_PER_LANDMARK = 13000 → clamp(round(N/13000),16,32), LANDMARK_MIN_COVERAGE_FRACTION = 0.9 override-proof, --landmarks knob (cap 128); live --check on the real binary: nodeCount 311,361 / edgeCount 677,126 / landmarkCount 24 / quantum 0.100 / coverage min/mean 0.980/0.980 — the canonical L=24 build, upload-ready
08-05 D-03 gate with constant-mirror; honest campaign; records tell the post-ALT truth Gate asserts record.epsilon.name === "OPTIMALITY_EPSILON_PCT" && pct === 0.1 BEFORE measuring (L258); reads the frozen record, never regenerates pairs; budget-gates drift guard ROUTE_CPU_DRIFT_GUARD_MS = 400 with the quoted post-ALT band; BUDGETS/KNOWN-LIMITATIONS/ROAD-GRAPH all quote the same gate lines (53 routed / 152.788 / 185.692 / 182.725 / 204.499) — mutually consistent, verified against the REVIEW.md cross-check

Required Artifacts

Artifact Expected Status Details
routing/src/graph.ts ARG2 single-authority codec ✓ VERIFIED Substantive + wired (decoded the real binary live via --check; consumed by bot tests 126/126)
routing/src/landmark.ts ONE landmark compute core ✓ VERIFIED All three exports + WR-04 i32 ceiling guard; consumed by build script + fixture builder + tests
routing/src/astar.ts ALT potentials, F1 containment ✓ VERIFIED cleanColumnsFor/activeL present; landmarkFrom absent; toTable-only (sound subset)
routing/scripts/measure-optimality-baseline.mjs Baseline recorder + shared pair core ✓ VERIFIED ARG1-version guard; exports consumed by measure-route-cpu
routing/test/fixtures/alt-baseline.json Frozen pre-ALT record ✓ VERIFIED 29.6 KB, coordinate-pinned, epsilon block; untouched (gate mirror proves per run)
routing/test/fixtures/mini-graph-arg1.bin Preserved ARG1 rejection vector ✓ VERIFIED 1668 B, byte-preserved; consumed by graph.test.mjs:139
routing/test/fixtures/mini-graph.bin Regenerated ARG2 fixture ✓ VERIFIED 1884 B; suite-wide consumption green
routing/scripts/measure-route-cpu.mjs CPU gate + --extended ✓ VERIFIED Budget constant untouched; extended mode shares the pair core
routing/scripts/measure-optimality-gate.mjs D-03 gate ✓ VERIFIED Mirror assert; GATE PASS re-run this session
routing/scripts/measure-astar-oracle-sweep.mjs 200-pair fresh oracle sweep ✓ VERIFIED WR-01 symmetric |Δ| fix present (L244); GATE PASS re-run this session
routing/scripts/build-road-graph.mjs Preprocessing stage + knobs ✓ VERIFIED Scaling rule, coverage gate, --landmarks, --check landmark facts
routing/test/rollout.test.mjs D-01 rollout locks ✓ VERIFIED RO1/RO2 pins green in suite; targets verified format-unaware
scripts/lib/budget-gates.mjs Re-anchored route-cpu law ✓ VERIFIED Drift guard 400; quoted c3 record; no next-milestone
docs/BUDGETS.md / docs/KNOWN-LIMITATIONS.md / docs/ROAD-GRAPH.md Post-ALT honest records ✓ VERIFIED Quoted numbers mutually consistent; ALT row flipped; ARG2 layout section present
routing/data/kl-roadgraph.v1.bin Canonical L=24 ARG2 binary (gitignored) ✓ VERIFIED On disk, 45.3 MB; decodes ARG2 with L=24/quantum 0.1/coverage 0.980
From To Via Status Details
astar.ts potential() ARG2 landmark tables graph.landmarkTo reads via cleanColumnsFor/activeL WIRED L233–242, L358–402
measure-route-cpu --extended measure-optimality-baseline import { generateCrossMetroPairs } WIRED L60, L110 — one pair set, two consumers
measure-optimality-gate alt-baseline.json reads frozen record + epsilon mirror WIRED RECORD_PATH L53; mirror assert L258 fires before measurement
build-road-graph preprocessing landmark.ts dynamic import of the ONE module WIRED L202; no second Dijkstra exists (grep across scripts = 0)
graph.test.mjs mini-graph-arg1.bin ARG1 decode-rejection vector WIRED L139
rollout.test.mjs upload script + worker-router structural grep pins WIRED RO1 pins the R2 key; RO2 pins no version branch — both targets verified clean
mini-graph.bin / bot test builders ARG2 encode path same encodeGraph authority WIRED bot 126/126 green after fixture regen

Data-Flow Trace (Level 4)

Not applicable to dynamic-UI artifacts (this phase ships no UI). The data-flow analog — real graph bytes → decode → search → gates — was exercised end-to-end this session: the 45.3 MB binary decodes (311,361 nodes / 677,126 edges / L=24), routes (23/25 routed in the CPU sample), and feeds both optimality gates with real measured seconds (D-03: 53 pairs; oracle: 182 routed pairs). No static/hollow data paths found.

Behavioral Spot-Checks (all run by this verifier, this host, 2026-10-25)

Behavior Command Result Status
Routing suite (A1–A13, G1–G11, L, S, RO suites) npm run routing:test 82 passed, 0 failed ✓ PASS
Bot suite (ARG2 fixture consumers) npm test -w bot 126 passed, 0 failed ✓ PASS
D-03 optimality gate (SC-2) node routing/scripts/measure-optimality-gate.mjs GATE PASS, exit 0 — 0 violations, max |Δ| 0.005% ✓ PASS
200-pair fresh oracle sweep (SC-2 pin) node routing/scripts/measure-astar-oracle-sweep.mjs GATE PASS: 0/200 |Δ| violations (182 routed, worst +0.000%) ✓ PASS
CPU gate (SC-1) node routing/scripts/measure-route-cpu.mjs GATE FAIL: p95 107.493 ms exceeds the 8 ms budget ✗ FAIL (honest — the SC-1 gap)
Binary identity + landmark facts node routing/scripts/build-road-graph.mjs --check routing/data/kl-roadgraph.v1.bin ARG2; L=24; quantum 0.100; coverage 0.980; sentinels 150,986 to / 1,365,034 from ✓ PASS
Budget-audit vectors node scripts/test/budget-audit.test.mjs 19/19 vectors ok ✓ PASS

(Overpass build NOT re-run per instructions; the on-disk binary is the canonical L=24 build.)

Requirements Coverage

Requirement Source Plan Description Status Evidence
SC3 (carry-over) 08-01..05 frontmatter Phase-5 criterion: fixture backend ladder + designed router-pending state ✓ SATISFIED (no regression) routing 82/82, bot 126/126; rollout pins hold; router-pending law intact
SC4 (carry-over) 08-01..05 frontmatter Phase-5 routing-class carry-over ✓ SATISFIED (no regression) Same suite evidence
Phase-8 requirement ("the budget record's numbers improve") ROADMAP §Phase 8 No new REQ ids; the c3 numbers improve ✗ BLOCKED The measured numbers did NOT improve (p95 107–186 ms vs the pre-ALT ~38 ms campaign band); the record honestly documents the non-improvement. Covered by the SC-1 gap above.
Orphaned requirements — none — REQUIREMENTS.md maps no additional ids to Phase 8 (grep: SC3/SC4 appear only as ROADMAP-level carry-overs)

Anti-Patterns Found

File Line Pattern Severity Impact
— — No TODO/FIXME/placeholder/stub patterns in any phase file (grep clean across all 7 scripts + 3 src modules) — —
routing/src/astar.ts 315–316, 515, 598 return null / return [] ℹ️ Info Fail-honest designed degradation (input validation, unreachable miss, empty path) — not stubs
measure-*.mjs various = [] accumulators ℹ️ Info Local accumulator init, not hardcoded empty data

Open code-review findings carried for the record (documented in 08-REVIEW.md, not re-litigated here): WR-03 (baseline recorder lacks oversampling — the frozen evidence base is 53 measured pairs, not ~100; maintainer-deferred, record immutable) and IN-01..IN-07 (doc-statement drift, defensive gaps in future-record paths). WR-01/02/04 verified applied: symmetric |Δ| compare at oracle L244, CPU3 honest-SKIP law, LANDMARK_I32_WEIGHT_CEILING guard at landmark.ts L131 — each with its fix commit (11e55c1, 95399ae, e77bbe9) present in history.

Human Verification Required

  1. The c3 escalation decision (the gap itself — belongs to the USER). Test: Choose the track: (1) direction-split potentials with a re-proven bidirectional meet rule (needs its own phase — skeleton work Phase 8's laws forbade), (2) Contraction Hierarchies (Phase-6 deferral), (3) Workers Paid reversal (needs explicit sign-off against the $0 law), (4) keep c3 as the designed degradation (current shipped posture; zero code). Expected: A recorded decision against docs/BUDGETS.md §c3 that unblocks either Phase 9 (option 4) or a new planned phase (options 1–2). Why human: Strategic trade-off across cost law, scope, and schedule — not decidable from code.
  2. R2 migration state (D-01's one-time upload). Test: node routing/scripts/upload-road-graph.mjs + --check roundtrip against R2 (maintainer-time, account-gated). Expected: The R2 object kl-roadgraph.v1.bin holds the ARG2 build (v2, L=24, coverage 0.980); production /api/route serves real routes. Until then, any deploy of the current Worker code is router-pending on every route (ARG1 bytes decode to null by design). Why human: R2 contents and deploy timing are outside the repo; the upload is deliberately manual.

Gaps Summary

One root cause, two failed criteria. The CPU win — the phase's core deliverable — did not land (SC-1), and therefore the c3 retirement correctly did not fire (SC-3). What DID land, verified end-to-end this session: the ARG2 layout (single decode path, fail-honest, exact-size law), the landmark machinery (module, build-stage integration, D-02 scaling rule, honest coverage/quantum gates, the canonical L=24 binary), optimality hardening beyond the plan's bar (D-03 gate + 200-pair fresh oracle sweep, both green — after the phase's own gates caught two real suboptimality bugs), and four records rewritten to the quoted post-ALT truth with zero retirement theater.

The remaining work is not a bug fix: the debug session proved a perfectly implemented two-sided ALT cannot beat haversine in this bidirectional configuration on a graph with sentinel fringes (0/24 clean columns), and the sound fast path (direction-split potentials) requires re-proving the BH meet rule — work this phase's untouchable lines forbade. This is the escalation decision recorded in docs/BUDGETS.md §c3 and 08-05-SUMMARY, and it belongs to the maintainer, not to a closure plan. No later milestone phase covers it: Phase 9 builds on the current posture, Phase 10 is the battery record, and Phase 11 (Engine B) moves routing client-side without promising the Worker path in-budget — so nothing here is deferrable.


Verified: 2026-10-25T14:43:22Z Verifier: OpenCode (gsd-verifier)

Decision addendum (2026-10-25, maintainer)

The SC-1 escalation decision was made: Contraction Hierarchies, as Phase 08.1 (inserted, "Routing Backend v3") — the only lever the measured evidence supports reaching the 8 ms budget. Direction-split potentials are NOT closed: the measured prizes (0.59× expansions unidirectional control; −41% transposed table) and the full proof-obligation surface are handed off in docs/ALT-DIRECTION-SPLIT.md as a standalone experiment (explicitly open to being worked with a different LLM/harness). SC-1 and SC-3 transfer to Phase 08.1; this phase's debt is the honest record above plus that handoff. SC-2's hardening stands as the phase's optimality proof.