Files
arah2/.planning/phases/08.1-contraction-hierarchies-routing-backend-v3-the-lever-that-cl
araharah-executor 67026b9483 docs(08.1): fix plan task ownership and broken verify gates
- 08.1-01 task 2: re-pin graph.test.mjs in-memory G-cases (G1/G3/G8/G9/G10/G11)
  and astar.test.mjs in-memory/ALT cases; suspend only committed-fixture G7 and
  A1/A2/A4/A5/A6 (the runner auto-discovers all suites and parses no argv, so
  task 2's verify could never exit 0 otherwise)
- 08.1-01 task 3: own un-suspension of G7 and A1/A2/A4/A5/A6 after the ARG3
  fixture regeneration
- 08.1-01 task 1: drop the cosmetic --test-name-pattern flag (ignored by the
  hand-rolled runner; full suite runs instead)
- 08.1-02 task 2: use grep -cF for the rollout decodeGraph call-site gate
  (BRE form exited 2 with 'Unmatched ( or \\(')
- 08.1-02 task 1: replace the no-op '|| test $? -eq 1' landmark gate with a
  'test "$(...)" -eq 0' count assertion that can actually fail
2026-10-26 00:54:01 +08:00
..